Q: I need a custom building, but what is the soonest I can get it?

A: Generally, it takes 45 days for your building to be manufactured and delivered. Every custom building is different and we do not necessarily have everything on hand to build it. It takes approximately 3-5 days for paperwork to process and another two weeks for materials ordered to come in. At that point, the building is scheduled into production to be built. After the build is completed, please allow an additional two weeks for delivery.